Pool & spa structure
Excavation, steel, gunite, plumbing and backfill.
Excavation and dirt removal
Excavation of the pool, spa and sunshelf, with all the dirt hauled off the site.
See details
Pool Excavation & Dirt Removal · 120 Linear Feet × $47.50
- Pool shell excavation and haul-off/removal of excavated dirt from the job site. Priced per linear foot.
Rebar and forms
Forms and engineered steel rebar for the floor, walls, steps, spa and beam, bonded per NEC 680 and inspected before gunite.
See details
Rebar & Forms · 120 Linear Feet × $50
- Layout and setting of forms around the pool perimeter to establish the shell shape and beam
- Supply and installation of steel rebar per engineered spacing and size, tied in a grid across the floor, walls, steps, benches and beam
- Rebar supports/chairs to hold proper clearance for the gunite
- Bonding of the steel per NEC 680 requirements (bonding inspection coordinated per permit)
- Steel inspection coordinated before gunite
Gunite pool, spa and sunshelf shell
Gunite shell for a 12' x 30' pool, a raised 7' x 7' spa (12" above the deck) and a 12' x 7' sunshelf, 3' to 5' deep.
See details
Gunite · 120 Linear Feet × $180
- Gunite (shotcrete) application for the pool/spa shell, built to the structural engineer's plans and Florida Building Code.
Perimeter piping and plumbing
Main drains, skimmers, returns and spa lines to the equipment pad, pressure tested twice and inspected.
See details
Perimeter Piping & Rough Plumbing · 1 Each × $4,800
- Before gunite: main drain lines installed and pressure tested
- After gunite and first backfill: trenching and PVC piping for skimmers, returns and suction lines to the equipment pad
- Rough-in of lines for the spa and pool features shown on the plans
- Second pressure test of the perimeter piping
- Inspection of piping, underground electrical and pressure test before the second backfill
Backfill and grading to deck level
Backfill in two stages, compacted and graded to deck level with slope away from the pool and house.
See details
Backfill & Grading To Deck Level · 1 Each × $3,200
- First backfill around the shell after gunite and form removal
- Second backfill in compacted lifts after the piping inspection passes
- Grading to the finished deck sub-grade with slope away from the pool and house
- Final leveling for the deck and cleanup of excess material